What is included in a turnkey commercial fit-out?
Everything between the landlord's shell and an occupiable space: civil and partitions, internal services, ceilings, flooring and finishes, joinery and workstations, supervision, snagging and handover. The defining feature is that one contractor holds all of it against one BOQ.
What is usually excluded?
Base-build works, HVAC plant, fire system tie-in, IT active equipment, loose furniture, approval fees and deposits, DG or UPS, and access control or CCTV. Ask for the exclusions in writing before comparing quotes — the cheaper number is often just the one that excluded more.
Who obtains the approvals?
Generally the contractor prepares and submits fit-out drawings, the landlord approves them, and malls run a separate process with their own standards and deposit. Settle who submits, who pays, and what happens to the programme if approval slips.
What should I receive at handover?
A closed snag list, as-built drawings, the electrical layout, warranties with models named, the hardware schedule with grade confirmation against the signed BOQ, and a written defect liability position. Agree the list at contract stage.
Is turnkey more expensive than appointing trades separately?
Per line, often slightly. In total, frequently not — separate trades create coordination gaps that cost real money and real weeks. Where separate appointment wins is when you have an in-house projects team to run the coordination.
How much does a turnkey office fit-out cost?
₹3,000–₹10,000 per sq ft of carpet area, all-in including MEP, HVAC and loose furniture, exclusive of GST. Wider in scope than the exclusions table above, which describes the market's common practice rather than our band. Before comparing it with any other figure, confirm the other is also on carpet area, also all-in, and also states its GST position. Many published bands state no basis at all, and among those that do, it is often not the basis attached to the rate.
How is turnkey different from design-and-build?
Turnkey describes the delivery scope; design-and-build describes who drew it. A turnkey contractor can build to your architect's set without having designed it, which keeps an independent party available to check the work.
Can the fit-out run while we stay occupied?
Yes, phased zone by zone with dust screens and out-of-hours working, but it lengthens the programme and carries a premium — a phased sequence cannot overlap trades the way an empty floor plate can. Agree the working-hours restriction before pricing.
How is a turnkey commercial fit-out paid for?
Projects start on a 20% deposit of the total contract value, adjusted against the final invoice. The balance is released against milestones tied to progress — material procurement, civil and carpentry completion, finishing and handover — and the exact milestone schedule is written into each project's payment schedule, because it moves with size, scope and site condition. Published rates are exclusive of GST. Because turnkey pricing is a single number over a wide scope, the milestone list is where you see what you are paying for and when — it is written into the project's payment schedule, not assumed.
How long does a commercial fit-out run?
Anchored to delivered work: a 600 sq ft premium office took five weeks, a restaurant six, a Hyderabad office roughly ten, and a 5,450 sq ft Chennai office roughly twelve from signed scope to handover. Your own date is estimated at BOQ stage and confirmed in writing. Anything outside the signed BOQ is a variation: costed and confirmed in writing before it is executed, with its own price and timeline impact.